Surat: The heavy engineering arm of L&T achieved yet another milestone by despatching the third steam generator (SG), ahead of schedule, for the indigenously developed 10 x 700 megawatt-electric (MWe) Pressurised Heavy Water Reactor (PHWR) fleet programme.
The despatch ceremony took place at L&T’s A M Naik Heavy Engineering Complex at Hazira in the presence of Nuclear Power Corporation of India Limited (NPCIL) director (technical) Rajesh V and his team.
Delhi Election Results 2025
The steam generator is meant for the Karnataka-based Kaiga Atomic Power Station (KAIGA) Units 5 & 6.
L&T achieved a global benchmark by delivering the first the steam generator in just 33 months.
Anil V Parab, a senior official of L&T Heavy Engineering & L&T Valves, appreciated both L&T and NPCIL teams for consistent fast-track deliveries, in line with the Department of Atomic Energy‘s (DAE) target to install 22 GWe nuclear power by 2032 and Viksit Bharat vision of 100 GWe by 2047.